Strata painting: how councils should plan and choose a contractor
The short answer
Plan the repaint from your depreciation report, fund it the way the Strata Property Act allows, and choose a contractor on a written scope rather than a headline number. Get at least two quotes that price the same surfaces, prep and coats, check proof of insurance, and read the warranty terms before council signs. Confirm the voting and funding steps with your strata manager or lawyer.
Start with the depreciation report
A strata repaint should not be a surprise. In BC, the depreciation report is the document that tells a council what is coming and roughly when.
Under section 94 of the Strata Property Act, a strata corporation must obtain a depreciation report from a qualified person, estimating the repair and replacement cost of major items and their expected remaining lives. The detail (who counts as qualified, deadlines, contents) sits in the regulations.
The BC government’s depreciation report page sets out how the rules changed:
- Effective July 1, 2024, the requirements were strengthened. All strata corporations with five or more strata lots, including bare land stratas, must obtain a depreciation report.
- Reports are on a five-year cycle.
- Councils can no longer defer the report with an annual 3/4 vote.
- Existing stratas in Metro Vancouver, the Fraser Valley or the Capital Regional District with no report, or a report received before December 31, 2020, had a deadline of July 1, 2026.
- Effective July 1, 2025, reports must be prepared by members of designated professions, such as professional engineers, architects and certified reserve planners.
For painting, the useful part is the physical component inventory. The government page says it is based on an on-site visual inspection where practicable, and gives each item an estimated service life over a 30-year horizon. It also identifies limited common property that owners maintain. The financial side includes a projected 30-year schedule of contingency reserve fund costs and at least three funding models, which the strata does not have to adopt.
So before anyone calls a painter, pull the report and find the line items for exterior coatings, trim, railings, doors and any other painted components. That tells you what the report expects and when.
Funding the repaint: contingency reserve fund or special levy
Section 92 of the Act requires every strata corporation to set up an operating fund and a contingency reserve fund, with owners contributing through strata fees. A repaint is usually paid from the contingency reserve fund, a special levy, or a mix of the two.
Spending from the contingency reserve fund (section 96). The fund can only be spent in line with its purpose and with approval. The vote needed depends on what the money is for:
- A majority vote at an annual or special general meeting covers repair, maintenance or replacement that is recommended in the most current depreciation report (among a few other listed purposes).
- A 3/4 vote at a general meeting is needed for expenses outside those categories.
That is a practical reason to keep the depreciation report current. If the repaint is in the report, the approval threshold is lower.
Raising a special levy (section 108). A strata corporation can raise money from owners with a special levy. Where each lot’s share is calculated under the standard sections of the Act, the levy needs a 3/4 vote at an annual or special general meeting. The resolution must state the purpose, the total amount, how each lot’s share is worked out, each lot’s share, and when it is due (or the instalment dates). Money raised by the levy has to be kept separate and used only for the stated purpose.
Section 1 of the Act defines a 3/4 vote as at least 3/4 of the votes cast by eligible voters present in person or by proxy, not counting those who abstain.
This is a summary of what the Act says, not legal advice. Councils should confirm the right vote, the wording of any resolution and the notice requirements with their strata manager or lawyer.
Writing the scope: surfaces, prep, products, coats
A painting quote is only as good as the scope behind it. If the scope is vague, every contractor prices a different job, and the council cannot compare them.
A useful written scope covers:
- Surfaces. Siding, trim, fascia, soffits, doors, railings, balconies, fences, parkade or stairwell walls. List what is in and what is out.
- Who looks after what. Section 72 of the Act says the strata corporation must repair and maintain common property and common assets. A bylaw can make an owner responsible for limited common property they have the right to use. If your bylaws put balconies or unit doors on owners, the scope should say so. Check your bylaws with your strata manager.
- Prep. Washing, scraping, sanding, caulking, spot priming and repairs to damaged wood. Prep is where quotes differ most, and where a paint job lasts or fails.
- Products. The product line, sheen and colours for each surface, or at least the standard the contractor will meet.
- Coats. The number of coats on each surface.
- Access. How the crew will reach each elevation.
- Warranty. What it covers and for how long, in writing.
Where the depreciation report or a building envelope consultant already describes the work, give that to every contractor so they all price the same thing.
Comparing quotes like-for-like
Once the quotes are in, lay them side by side against the scope. The question is not which number is lowest. It is which quotes price the same job.
What moves the price on a strata repaint:
- The number of surfaces and elevations included
- How much prep the building needs, and how much repair turns up along the way
- Access: ground level, ladders, lifts or scaffolding
- The product line and the number of coats
- Working around residents, parking and balconies
- How the work is phased across the complex
If one quote is far from the others, check whether it leaves something out, such as a second coat, a set of surfaces or repairs. Ask each contractor to confirm in writing how they handle rot or damaged wood found once the work starts.
Ivy League Painting gives every strata job a free, on-site, written quote with the scope set out, so the council has something it can compare and approve.
Living with the work: notices, access, balconies, scaffolding
A repaint happens around people’s homes. The quote should explain how the contractor will work around residents, and the council should plan its notices before the start date.
Things to settle with the contractor and your strata manager:
- Notices. When owners and tenants will be told about each phase, and how.
- Balconies and patios. Who clears them, and what happens to plants, furniture and barbecues.
- Windows and vents. When windows must stay closed, and on which elevations.
- Parking and access. Which stalls, walkways or entrances are affected, and when.
- Scaffolding or lifts. Where they go and how the site is kept safe for residents.
- A single contact. One person at the contractor who answers owner questions.
Ivy League Painting replies to enquiries within one business day.
Checklist before the council signs
Before the contract is signed, the council should have:
- The current depreciation report, and the line items the repaint covers
- The approved funding (a contingency reserve fund resolution, a special levy resolution, or both), confirmed with your strata manager or lawyer
- A written scope that every quote prices
- At least two comparable written quotes
- Proof of the contractor’s liability insurance
- The warranty terms in writing
- An agreed plan for notices, access and resident questions
- A named contact at the contractor
Ivy League Painting carries $5 million liability insurance and offers a 3-year, 100% satisfaction guarantee. It holds a BBB A+ rating and a 5.0 rating on Google from 31 reviews. Jack and Henry run the company from Tsawwassen and have been painting in Delta for 10 years. See strata painting for how they work with councils and property managers, and commercial painting for other multi-unit and business properties.
When your council is ready, get a free quote.
Frequently asked questions
How often should a strata building be repainted?
The Act does not set a repaint interval. The best guide is your depreciation report, which estimates the remaining life of each major component, including painted surfaces. Under the rules in effect since July 1, 2024, stratas with five or more lots get a new report on a five-year cycle, so repaint timing is reviewed regularly.
Who approves a strata repaint?
The owners approve the funding at a general meeting. Under section 96, a majority vote can approve contingency reserve fund spending on repairs recommended in the most current depreciation report, while other spending needs a 3/4 vote. A special levy under section 108 generally needs a 3/4 vote. Confirm the exact vote and resolution wording with your strata manager or lawyer.
Can a repaint be paid for with a special levy?
Yes. Section 108 lets a strata corporation raise money from owners with a special levy. The resolution must state the purpose, the total amount, how each lot’s share is calculated, each lot’s share and when it is due. The money must be kept separate and used only for that purpose. If shares are calculated a different way, a unanimous vote is needed. Confirm the vote and resolution wording with your strata manager or lawyer.
Should we ask for an insurance certificate?
Yes. Ask every contractor for proof of liability insurance with their quote, and check it against what your strata manager expects. Ivy League Painting carries $5 million liability insurance on every job, strata buildings included.
What warranty should a council ask for?
Ask for the warranty in writing: what it covers, how long it lasts and how to make a claim. Ivy League Painting offers a 3-year, 100% satisfaction guarantee. Compare warranty terms across quotes, not just the length.
When should a strata exterior repaint be scheduled?
Exterior paint needs the right weather. Benjamin Moore recommends planning exterior painting for temperatures between 1.7 and 37.8 degrees C with humidity as low as possible, avoiding direct sun and rain. Since the funding vote has to happen first, councils that want the work done in dry weather should plan the general meeting well ahead.